Lempster Wind Farm East Lempster, NH

Lempster Wind Farm East Lempster, NH

Lempster Wind Farm East Lempster, NH

Lempster Wind Farm East Lempster, NH Owner Lempster Wind, LLC Project Type Sitework for a Wind Farm Sargent Corporation’s Role Sitework contractor Start/Finish December 2007—September 2008 Turbines 12 Description/Significance This project included construction of 5 1/2 miles of access roadway and 12 turbine pads. Steep terrain at eleva- tions over 2,000 feet and access to the job site were the most difficult h