Case Study

Meter Skid

Meter Skid

Pages 1 Pages

Executive Summary TorcSill exercised its in-house Engineering and local Operations presence for a quick- acting, solutions-focused approach, which proved invaluable for its customer by ensuring no further delays on this foundation replacement Meter Skid Project. Challenges Quick turnaround was critical for this Project, after the initial attempt to install a concrete foundation was unsuccessful. Originally planned for an early morning installation at a site inaccessible for large concrete trucks, the concrete lacked the additives to cure properly in extreme heat. Unforeseen delays on site pushed this concrete pour into the heat of a 100-plus degree day on the Texas Gulf Coast, leading to a nonuniform and unusable foundation. What We Did Called into quick action by the owner, Torc